Copying Task Fields to Resource Fields

$
0
0

Hi

I have a need to copy data from a task field to a resource field.  Basically I want to add the Project Name to every activity against each resource name in the Resource Usage View.  I have a piece of code from Jack Dahlgren that will copy Task Field data to an Assignment Field but I need it to go in to a custom Resource Field, say Text1.

Any help/guidance would be appreciated as I am stuck.

Kind regards

Tony